Greggs Finmere - EG On The Move
Kiosk
767 sq ft
9-Day Site Installation
Finmere, Oxfordshire, UK
Retail / Drive-To
2 Modules
No items found.

Project Details

Client: EG On The Move

End User: Greggs plc

Location: Finmere, Oxfordshire

Date of Order: 4 June 2026

Practical Completion: 25 June 2026

Store Opening: 9 July 2026

Modu-Lite Project Duration: 3 weeks from order to practical completion.

Following handover, Greggs completed the internal store fit-out, with the store opening two weeks later on 9 July 2026.

Project Timeline

Day 1 - Live on Site

Days 1–3 - Structure Rising

Mid-Programme - Building Takes Shape

Day 7 - Watertight & Boarded

Day 8 Onwards - External Finishes Underway

Project Complete — Shell Handed Over Snag-Free