1150 Model

1150 sq ft
10-14 weeks

The 1150sqft modular drive-thru unit, purpose-built for retail parks and roadside locations. Manufactured entirely off-site, it delivers a branded, repeatable Starbucks specification without the disruption, risk, or cost overruns of a traditional build. From design freeze to open doors in as little as 10-14 weeks, the 1150 model is engineered for operators who need speed, predictability, and a premium result - at scale.

Footprint:
1150 sqft
Use Case:
Drive-Thru Coffee Unit / Retail Park Pod
Build Type:
Fully modular off-site manufactured drive-thru
  • Starting cost for build - £160k
  • Civils - £230k
Typical Total Project Cost: E390k
Build Programme / Lead Time
  • Design Freeze to Manufacture: 2–3 weeks
  • Factory Build Duration: 4–6 weeks
  • Site Preparation: 2–4 weeks
  • Installation & Commissioning: 3–7 days
  • Typical Total Lead Time: 10-14 weeks
Key Commercial Advantages
  • Reduced site disruption
  • Fast deployment for multi-site rollouts
  • Lower preliminaries vs traditional build
  • Predictable programme and cost certainty
  • Repeatable branded specification
  • Scalable national rollout capability

Ready for delivery?

We’re able to get your new modular facility up and running in up-to 14 weeks, generating you income in record speeds.