1150 Model
1150 sq ft
10-14 weeks
The 1150sqft modular drive-thru unit, purpose-built for retail parks and roadside locations. Manufactured entirely off-site, it delivers a branded, repeatable Starbucks specification without the disruption, risk, or cost overruns of a traditional build. From design freeze to open doors in as little as 10-14 weeks, the 1150 model is engineered for operators who need speed, predictability, and a premium result - at scale.
Footprint:
1150 sqft
Use Case:
Drive-Thru Coffee Unit / Retail Park Pod
Build Type:
Fully modular off-site manufactured drive-thru
- Starting cost for build - £160k
- Civils - £230k
Typical Total Project Cost: E390k
Build Programme / Lead Time
- Design Freeze to Manufacture: 2–3 weeks
- Factory Build Duration: 4–6 weeks
- Site Preparation: 2–4 weeks
- Installation & Commissioning: 3–7 days
- Typical Total Lead Time: 10-14 weeks
Key Commercial Advantages
- Reduced site disruption
- Fast deployment for multi-site rollouts
- Lower preliminaries vs traditional build
- Predictable programme and cost certainty
- Repeatable branded specification
- Scalable national rollout capability